Project Type
Wastewater Treatment Plant
Project Owner
HDR Engineering
Project Location
South Dakota, USA
The Water Reclamation Facility South Plant Improvements – Phase 2 project which includes preliminary design services for phases 2, 3, and 4. Phase 2 will address the South plant’s capacity limitations which includes insufficient clarifier surface area and poor control of process aeration.
The project will address these issues with the installation of two additional secondary clarifiers, the replacement of all existing pumps, complete with associated piping.
The existing process blowers will be replaced with better turn down capabilities which will allow a new aeration control system to be implemented. Yard piping modifications will also be part of the project to incorporate the new infrastructure and upsize the lines as required.
Complete fabrication and delivery of 1 x ∅34m tank diameter and 1 x ∅36m tank diameter clarifiers made from 316L SS.